Construction Project Steps
Phase I: Excavation & Foundations (~300 000$)

ID

Step

Name

Start

State

1

1

Construction Permit

 

 

2

1.1

Decontamination of Terrain (Fondex)

May 06

completed

3

1.2

Revision of Plans & Approval

 

completed

4

1.3

Printing of Plans

 

completed

5

1.4

City Permit

June 06

completed

9

2

Contractors & Devis

 

 

10

2.1

Distribution of Plans and Specifications

 

completed

11

2.2

Choice of General Entrepreneur

July 06

completed

12

2.3

Signature of Contrat for Phase I

August 06

completed

13

2.4

Choice of Contractors for Phase I

August 06

completed

14

3

Field Work

 

 

15

3.1

Surveying

7 August 06

completed

16

3.2

Excavation

8 August 06

completed

17

3.3

Fence around the Field

9 August 06

completed

18

3.4

Inspection and Validation

18 August 06

completed

19

3.5

City Services (water, elec, ?)

21 August 06

completed

20

4

Foundations

 

 

21

4.1

Framework & Workshop Drawings

21 August 06

completed

22

4.2

Plaques d'ancrage

28 August 06

completed

23

4.3

Cement Purchase

Sept & Oct

completed

24

4.4

Setting of Footings & Steel

28 August 06

completed

25

4.5

Cement & Foundation Framework

Sept. & Oct

completed

26

4.6

Foundation Certification

October

completed

27

4.7

Foundation

 

reported

28

4.8

Drainage

October

completed

29

4.9

Cleaning of Field

November

in progress